[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

dam-l Epupa Decision Looms/LS



>From The Namibian, Sept. 18, 1998:


       Dam decision looms

       CHRISTOF MALETSKY

       NAMIBIA and Angola will meet at the end of October to make a final
       assessment of reports submitted by the consultants working on the
feasibility
       study of the controversial Epupa hydro-electric power dam in the Kunene
       region.

       Reports have already been submitted by a subcommittee from the two
       countries.

       The Namibia-Angola Permanent Joint Technical Commission (PJTC)
       meeting has been set down for October 29-30 in Windhoek. It is
likely to be
       the last meeting to make final recommendations to the two Governments.

       Deputy Director in the Ministry of Mines, Fernando Vahekeni, said the
       meeting was expected to take place but did not want to go into
detail about it.

       When the PJTC met in Windhoek last time, it pinpointed some shortcomings
       in the report by the consortium of consultants - Namang - comprising of
       Namibian, Angolan, Swedish and Norwegian companies and said there it was
       necessary to verify some facts before the project could finally be
concluded.

       "With due consideration of the problems ... the PJTC was not in a
position to
       discuss the matter of the selection of the single site (Epupa or
Baynes) for
       implementation as envisaged.

       "Instead, this topic has been postponed for discussion and
formulation of the
       final recommendation to the two governments at the next PJTC meeting,"
       the joint chairmen of the PJTC, Siseho Simasiku (Namibia) and Armindo
       Gomes Da Silva (Angola), said at the time.

       "The major shortcomings related to the incomplete consideration of
       mitigation measures, the lack of a complete proposal for an environmental
       management and post-construction monitoring plan, inconclusive work
       performed on the bilateral agreement and the non-inclusion of the
terms of
       reference for the phase three work," the statement said.

       The study contained comments on the project by the Supervision Committee
       for the Feasibility Study (SCFS), and other organisations such as
the World
       Conservation Union (IUCN) and the Norwegian Water and Energy
       Administration Directorate (NVE) which were specifically requested by the
       PJTC.

       In spite of the statement, sources claimed that the two governments were
       locked in a war of words over whether the controversial scheme should be
       constructed at the Epupa or Baynes site.

       Inside sources claimed that while Namibia wanted Epupa, their Angolan
       counterparts were keen on the Baynes site and that everything had to
do with
       "international politics".

       "Both sides have very strong arguments and claim that the project
might as
       well be abandoned if neither of them can get their desired results,"
a source
       told The Namibian.

       The Angolans are believed to be keen on the Baynes site because it
will mean
       they will have a good chance of obtaining international funds to
renovate the
       Gove dam inside Angola which was damaged during the civil war and has
       not been repaired since 1975.

       "It will also mean that development will come to the Huambo area - which
       has been a battle field - but everything will depend on the peace
process in
       Angola," noted a source.

       It is well known fact that Namibia is not keen on the Baynes site. The
       Government sees it as too small, despite its environmental and social
       advantages compared to the possible other sites. In sharp contrast
the Epupa
       site is regarded as a prestige site by Namibia.

       Namibia also cites the faltering peace process in Angola, and the
millions of
       dollars needed to repair the Gove dam as factors in favour of the larger
       Epupa site. New fighting was reported in the Gove area last week.

       The Epupa site is seven kilometres downstream from the falls and is
likely to
       displace some 700 Himba people as well as flood the falls. The area
flooded
       at the Baynes site, some 40 kilometres downstream from the Epupa falls,
       would be 94 square kilometres while Epupa would cover more than 250 sq
       kilometres.

       The consultants pinpointed Baynes as the best option in October 1996 but
       Epupa was controversially included in a move that cost the taxpayers
of the
       two countries N$3 million.

       Also:

       Epupa up-date



       September 18, 1998

                                Click here to return to story index




::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
      Lori Pottinger, Director, Southern Africa Program,
        and Editor, World Rivers Review
           International Rivers Network
              1847 Berkeley Way, Berkeley, California 94703, USA
                  Tel. (510) 848 1155   Fax (510) 848 1008
                        http://www.irn.org
::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::