[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

dam-l LS: The Hindu: Too early to rejoice over Narmada verdict?



Too early to rejoice over Narmada verdict?

Date: 24-02-1999 :: Pg: 14 :: Col: d

By Kalpana Sharma

MUMBAI, Feb. 23.

The celebrations in Gujarat over the recent Supreme Court interim
order  allowing  the authorities of the  Sardar  Sarovar  Project
(SSP) to resume construction of the dam on the river Narmada gave
the impression that all the hurdles had been cleared. The Gujarat
Chief Minister, Mr. Keshubhai Patel, was called ``Sachha Sardar''
and the rhetoric conveyed ``victory'' for Gujarat and defeat  for
the  anti-dam  campaigners. Such a conclusion,  however,  may  be
premature.

In  its  order of February 18 during the final  hearings  in  the
public  interest litigation filed by the Narmada  Bachao  Andolan
(NBA) in 1995, the Supreme Court gave the Sardar Sarovar  Narmada
Nigam Ltd. (SSNNL) permission to re-start construction on the dam
and raise the height from the current 80.3 metres to 85 metres.

Construction  work had been suspended when hearings on  the  case
began  in  1995. But the Apex Court also laid down  an  important
caveat,  one that is at the root of the problem  confronting  the
SSP.

The Supreme Court has asked Justice P. D. Desai (retd.), who will
head a ``Grievance Redressal Committee'', to report to the  court
by April 9 whether the rehabilitation of the oustees resettled so
far  has been satisfactory. Justice Desai's efforts  will  follow
those of a committee set up just as the hearings began in 1995 to
look into the same issue.

In  1993, the Centre had constituted a five-member  committee  to
look  into  several aspects of the SSP,  including  environmental
impact and resettlement. When the NBA filed its case, the Supreme
Court  asked  the  same committee,  partially  reconstituted,  to
submit another report. While one of the members of the committee,
Mr.  Ramaswamy  Iyer, former Union Water Secretary, had  given  a
separate note, the committee had also submitted several unanimous
recommendations which were never made public.

The committee had highlighted the serious difficulties that  were
already apparent on the issue of resettlement and had recommended
construction  in stages, so that at each point  the  resettlement
question   could  be  satisfactorily  addressed.  It   had   also
recommended the appointment of an ombudsman to hear grievances of
oustees. This report is still with the court. It is therefore not
clear  what new light another committee can shed in a  matter  of
six weeks on a question that has been investigated by others.

Furthermore,  in  the  course of the hearings in  the  last  four
years, the resettlement issue was constantly before the court  as
the  mega-  project  will  lead to  the  displacement  of  33,000
families  in  Madhya Pradesh, 3,100 in Maharashtra and  4,600  in
Gujarat. As late as last year, the Madhya Pradesh Government  had
filed an affidavit stating that as many as 19 of the resettlement
sites  offered by the Gujarat Government for people who would  be
affected  if the height of the dam was raised to 85  metres  were
unsuitable  for various reasons. If this was the  situation  last
year, it is unclear how the hurdles to finding suitable land  for
potential oustees can be tackled in such a short period.

In  any case, according to the Narmada Waters  Disputes  Tribunal
(NWDT)  award,  land for oustees should be  identified  one  year
before  submergence  and  resettlement should  be  completed  six
months  before submergence. If the SSNNL successfully raises  the
height of the dam to 85 metres before the monsoon, that is in the
next  three months, how will the Governments of  Gujarat,  Madhya
Pradesh and Maharashtra resettle the people whose homes and lands
will  be  submerged during the monsoon as a  consequence  of  the
raised height? According to official figures, which have often in
the  past  turned out to be under-estimates, of the  365  project
affected persons (PAPs) who would need to be resettled in  Madhya
Pradesh,  only  229 have moved so far. In Maharashtra,  220  PAPs
will need to be resettled.

The  areas  that will be submerged if the dam height  reaches  85
metres  by  early June are the villages of Bhil and  Bhilala  and
lands in Alirajpur, Kukshi and Badwani tehsils in Madhya Pradesh,
Akrani and Akkalkuwa tehsils in Maharashtra and Chhota Udepur and
Nandod taluks in Gujarat.

Another  question is about the height of 85 metres. Depending  on
Justice   Desai's   report,  the  court  could   permit   further
construction up to 90 metres. But on its own admission, the SSNNL
acknowledges that the dam will only be able to serve any  purpose
in  terms of irrigation water or electricity once it crosses  110
metres. Thus, even at 90 metres, the dam will not be functional.

Meanwhile,  the  other  major  issue  that  the  Madhya   Pradesh
Government  has  raised  - that the final height of  the  dam  be
lowered  to  436 feet because water flows in the  river  are  now
lower  than  when  the  NWDT  award  was  determined  -   remains
unresolved.

What the order is likely to result in is forced resettlement even
if  in  theory it is called ``voluntary''. When  people  get  the
signal  that  the dam is going to be  constructed  regardless  of
factors such as adequate rehabilitation, they might be tempted to
take  whatever is offered, however inadequate, rather  than  hold
out  for  a  fair resettlement package. This is  the  reason  the
Gujarat Government is in such a celebratory mood.